Summary
A $2.2 million contract with KRG Utility plus $281,304 in CHA Consulting engineering services would rehabilitate sewers in the Upper Boulding Branch basin.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 29, 2026.
Impact analysis
Combined contract and engineering costs of roughly $2.49 million.
Residents and businesses in the basin served by the rehabilitated sewer lines.